Hammond Street Stormwater upgrade - Stage 1

May 11, 2016

Blackley Construction has been contracted by Council to install a new stormwater system.

This work is due to commence on the week beginning 23rd May.

The contract period will be for 6 weeks and involves the installation of a new headwall at the Tutaenui Stream, the laying of 825/750mm dia concrete pipe and the associated manholes up as far as Hair Street.

Stage 2 has been identified to be done next year, and will run through to the roundabout on Broadway.