Work begins on removing Marton Swim Centre roof

On Thursday 26 November, contractors began removing the existing roofing materials, marking one of the most visible stages of the $6 million redevelopment project so far.

November 27, 2026

Marton Swim Centre

Once this initial work is completed, a large crane will be brought onto the site to assist with removing the remaining roof structure, including the existing timber beams.

The next stage will involve lifting and installing the new steel roof trusses, which will form the supporting structure for the replacement roof.

Work will pause over the Christmas holiday period before contractors return in the new year to complete any remaining truss installation and begin preparations for the new ETFE roofing system.

ETFE is a lightweight, durable roofing material that will replace the swim centre's existing roof. The initial work in January will involve preparing the structure for the ETFE material, rather than installing the material itself, which will follow at a later stage.

While the programme remains subject to construction progress and weather conditions, the roof replacement marks a significant step towards reopening this important community facility.

The redevelopment remains on track for its targeted completion in time for the 2027/28 summer season, although a confirmed reopening date has not yet been set.