We’re moving to a new email system, and think it’s a great opportunity to tidy up our subscriber list. If you'd like to receive updates from us to your inbox, such as our monthly Rangitīkei Connect newsletter, Council consultations, and opportunities to share your views on local projects, plans, and decisions, then you can subscribe here.

Water Services

Stormwater upgrades, Marton

We’re installing a new stormwater pipe on Skerman Street (between Barnett Drive and Bond Street) that will help to reduce pressure on the network and improve some known surface flooding issues in that area.

What to expect:

  • Work starting from Monday 13 April and estimated to be completed in 2 – 3 months.
  • Traffic will be down to one lane with stop/go or traffic lights in place day and night
  • No parking near the work site
  • This is a truck route, so please take extra care when travelling through

We’re aiming to have two-way traffic flowing on weekends where possible, but that will depend on site conditions.


Calico Line watermain replacement

We're installing a new watermain on Calico Line from the bridge over the Tūtaenui Stream through to Nga Tawa School.

What to expect:

  • Work starting from Tuesday, 21 April and is expected to take two months to complete.
  • Traffic will be down to one lane with stop/go or traffic lights in place day and night
  • This is a truck route, so please take extra care when travelling through